Actions
Test Case #30802
openDo Flight Overall QA
Start date:
12/04/2025
Due date:
12/05/2025 (about 4 months late)
% Done:
90%
Estimated time:
16:00 h
Spent time:
remarks:
DB Changes:
Keys & Permissions:
Areas Affected:
Files Changed:
Description
Flight - B2C , Inhouse Flow
Sales report
Booking Actions - Ticketing/Cancel/Sync/Void/Refund actions
Blank Booking
User creation and Update - B2C and Admin
TQR Edit/Update
Markup/Discount
Direct Payment - Via form and TQR flow
Add check list
Files
Updated by Nitheesh K N 4 months ago
- Due date changed from 12/12/2025 to 12/05/2025
- Start date changed from 12/11/2025 to 12/04/2025
Updated by Gopika Shaji 4 months ago
- File tyarty checklist.xlsx tyarty checklist.xlsx added
- % Done changed from 0 to 60
Verify tyarty
Updated by Gopika Shaji 4 months ago
- File tyarty checklist.xlsx tyarty checklist.xlsx added
- Status changed from In Progress to Fixed not Tested
- % Done changed from 60 to 90
done qa on tyarty
Actions