Bug #26054

closed

Dynamic Package | Makkaha - Madinah Search result page issue

Added by Nitheesh K N 3 months ago. Updated 3 months ago.

Status:
Closed
Priority:
Normal
Assignee:
-
Category:
Functionality
Target version:
Al Maqaam - Pending features
Start date:
08/29/2025
Due date:
09/01/2025
% Done:

100%

Estimated time:
3:00 h
Spent time:
remarks:
DB Changes:
Keys & Permissions:
Areas Affected:
Files Changed:

Description

Search Dynamic package with Makkaha - Madinah below issues founded

1. Flight + Accommodation page, while click continue button next it's displayed hotel page. result required in this scenario in this page no need to redirect to hotel page show Activity selection popup with yes and no button if click yes it should be redirected to activity page and if clicked no it should be redirected to summary page

2. In above scenario change default transfer and proceed up-to summary / pax page and click flight + accommodation tab at this time already selected transfer not displayed as selected. Please fix the issue and make sure selected transfer displayed as selected

Reference screenshot attached here


Files

RecordedVideo (14).mp4 (8.99 MB) RecordedVideo (14).mp4 Nitheesh K N, 08/14/2025 01:33 PM
trans (2).zip (26 MB) trans (2).zip Rahul P K, 09/02/2025 04:39 PM
Actions #1

Updated by Vivek V 3 months ago

  • Due date set to 09/01/2025
  • Status changed from New to Assigned
  • Assignee set to Sachin Suresh
  • Target version set to Pending features
  • Start date changed from 08/14/2025 to 08/29/2025
  • Estimated time set to 1:30 h
Actions #2

Updated by Sachin Suresh 3 months ago

  • Status changed from Assigned to In Progress
Actions #3

Updated by Sachin Suresh 3 months ago

1>issue fixed

Actions #4

Updated by Sachin Suresh 3 months ago

2>2nd issue will be fixed once the transfer module reimplemenation and optmizations are completed
holding the task

Actions #5

Updated by Sachin Suresh 3 months ago

  • Status changed from In Progress to On hold
Actions #6

Updated by Sachin Suresh 3 months ago

  • Status changed from On hold to In Progress
  • % Done changed from 0 to 50
Actions #7

Updated by Vivek V 3 months ago

  • Estimated time changed from 1:30 h to 3:00 h
Actions #8

Updated by Sachin Suresh 3 months ago

  • Status changed from In Progress to Fixed not Tested
  • % Done changed from 50 to 100

2>issue fixed

Actions #9

Updated by Rahul P K 3 months ago

1.fixed
2.fixed